@ sobetra we celebrate labour day everyday
on-going works…
- Excavation to level and compaction to access culvert 45+554 lhs
- Casting bed
- Opening of drain at km 34+478
- Backsplopping and opening up drains at km 48+400 to km49
- Excavation to level for access culvert 45+404 lhs
- Casting surround to access culvert 45+360lhs